Example 9 — Manufacturing services and capacity utilisation risk
Chapter I · Example 2 (risk) · ¶1.84, 1.87, 1.91, 1.102 · Company A · Company B
OECD Guidelines 2022The parties
What happens
- Company B builds and equips its plant to Company A's specifications, and employs and trains competent manufacturing personnel.
- Company B makes products for Company A, to technical requirements and designs that Company A provides.
- Company A determines the volume levels; Company B determines production scheduling on the basis of those volumes.
- Company A runs the supply chain, which includes procuring components and raw materials, and it carries out regular quality checks of the manufacturing process.
- Under the contract, the capacity utilisation risk and the supply chain risk are assumed by Company A.
The questions
Company B has incurred fixed costs, but as Company A determines the volumes, Company B cannot manage their recovery by deciding over how many units they are spread. Each of the two companies has the financial capacity for its respective risks.
Who should be allocated the risk that the plant is under-utilised?
As before, Company A runs the supply chain and the contract specifies that it assumes the supply chain risks. But when key components were not secured on time, Company A did not reimburse Company B.
How does the risk analysis deal with the supply chain risk now?
Related: Section D.1.2.1.3 (step 3: functional analysis in relation to risk) · ¶1.88 (step 4(i): is the contractual assumption of risk followed in the parties' conduct?) · ¶1.98 (step 5: allocation of risk)